Durrat Al Bahrain

ENGINEERING

• Challenges Faced in preparing the Project Design

  1. Determining of the final reclamation at +2.6mCD
  2. Removal of unsuitable material from south Crescent and Hotel Island with limitation on removing excessive quantities at minimum costs
  3. Beach design from limited resources of sand.
  4. Value engineering exercise carried out for an economic use of rock resulting in the use of 15 different grades of armor and under layer rock.
  5. Use of three different grades of geotextiles in respect of different grades of rock.
  6. Design of Toe Bunds and Groynes
  7. Final plot levels in relation to perimeter rock revetment levels

• Hydraulic Impact
Increase in the sea bed levels due to dredging from north borrow areas required a redesign of the rock revetments, especially at the atoll heads

• Construction Techniques used in Dredging and Reclamation

  1. To obtain the best available material from a very complex sea bed and predetermined boundaries required excessive numbers of bore holes to be drilled. Further pumping with a dredger of capacity 50-60,000cum/day had limitations in getting the placement for the best material in relation to the location.
  2. Setting Out for construction of Islands was a challenge as it deviated from the conventional straight to curved boundaries.
  3. Dredging to minimum depth of -3.0mCD regardless of quality of material
  4. Reclamation was a 2 stage process with first stage filling taken to about +1.0m CD and the next stage to the final level of +2.6m.
  5. First stage filling done by using spill barge and the next stage by shore pipe lines with land based equipment. Diffusers were used for control of placement.

• Statistics

  1. Total dredged volume is 34.0million cum
  2. 65km of rock revetments
  3. 1.4million cum or 2.3million tons of rock used in revetment construction
  4. Length along central axis of Atoll 2.Km, Petal 0.7Km
  5. Perimeter length of Atoll 4Km, Petal 2.4Km and Hotel Island 7.0Km